The Construction Schedule for Our Pakchong Retirement House Build Project

Below is the construction schedule (or programme – program in American) showing the sequence of building our retirement house in Pakchong (Pak Chong), Thailand. Each activity and the duration is shown.

The schedule (program) has been prepared by our builder and demonstrates the high quality of the builder we have chosen to build our retirement house.

The construction schedule has been translated from Thai to English by a non-technical translator, therefore some of the activity descriptions may not be crystal clear in English.

The schedule starts with the signing of the construction contract on January 2nd, 2011, and shows completion on June 24th, 2011 – a total time from start to completion of 6 months.

Download A .pdf Version Of The Construction Schedule

The image below is of a size small enough to fit on the web page. Just click here or click on the image and a full-size version in .pdf form will open for you in a new browser window. You can then save it to your PC.

Image of the Pakchong Retirement House Build Construction Schedule

The Construction Schedule for Our Pakchong Retirement House Build Project

Above, a small sized image of the construction program for our house in Pakchong. This was prepared by our builder to go with the construction contract that we signed on January 2nd, 2011. Construction work started on site on January 6th, 2011 and is schedued to finish on June 24th, 2011.

Click on the image to see a full-size version of the construction programme. (Or program as the Americans spell the word)


Click to join the Announcement List and get a notification when the website is updated


Be Sociable, Share!

2 Responses to “House Build Construction Schedule”

  • TJ:

    Congratulations on starting your project. Are you going to update this page regularly?

    [Reply]

    admin Reply:

    Hello and thanks for your comment.

    Yes, I am making a new progress update page right now. It will be ready in a day or two.

    Why not join the Announcement List and get an automatic notification whenever I post something interesting on the website?

    Just go to the website at and put your name and email in the Form at the top where it says “Keep Updated”.

    Best Regards

    Alan Brown

    [Reply]

Leave a Reply

Recommended
make Money in Thailand Logo
Post Categories
Keep Updated
Join the Announcement List and receive an email when something interesting is added to the blog or website.

 

Ads by Google